Inspection & test plans
Hold points and witness points as live tasks — the work can't pass a hold point until the inspection is recorded with evidence.
Record an inspection
Call with the configured ITP name and work area. To resume, name the existing inspection; its unresolved checkpoints will guide the call.
| ITP | Work package | Checkpoints | Hold points | Status | Last inspection | |
|---|---|---|---|---|---|---|
| ITP-C-011 | Concrete — L15 slab pour | 12 of 18 | 2 open | Hold point open | 23 Jul | |
| ITP-S-007 | Structural steel — transfer level | 9 of 9 | 0 | Complete | 18 Jul | |
| ITP-W-003 | Waterproofing — basement tanking B2–B1 | 4 of 11 | 1 open | Hold point open | 20 Jul | |
| ITP-F-002 | Facade panels L10–14 | 0 of 14 | 3 open | Not started | — | |
| ITP-E-005 | Electrical rough-in L8 | 6 of 10 | 0 | In progress | 22 Jul | |
| ITP-H-004 | Hydraulic risers L10–12 | 3 of 8 | 0 | In progress | 21 Jul | |
| ITP-C-010 | Concrete — L14 slab pour | 18 of 18 | 0 | Complete | 11 Jul | |
| ITP-M-006 | Mechanical ductwork L6–8 | 2 of 12 | 0 | In progress | 16 Jul | |
| ITP-F-001 | Fire stopping — L1–9 penetrations | 0 of 16 | 0 | Not started | — |