History
Browse your conversations, routines, documents, and usage
| File | Project | Action | When |
|---|---|---|---|
Delay notice — storm 23 July.docx | Northgate Tower | createdby Marcus Ellington | 24 Jul, 14:10 |
Site diary — 23 Jul.pdf | Northgate Tower | uploadedby Marcus Ellington | 23 Jul, 18:02 |
Subcontract General Conditions — Meridian Facades.docx | Northgate Tower | revisedby Marcus Ellington | 23 Jul, 11:24 |
Site meeting — L15 slab pour.m4a | Northgate Tower | meetingby Marcus Ellington | 22 Jul, 18:23 |
Progress claim SC-001.pdf | Northgate Tower | decisionby Marcus Ellington | 22 Jul, 22:24 |
SC-002 payment schedule.xlsx | Riverside Stage 2 | uploadedby Marcus Ellington | 22 Jul, 09:40 |
Facade package RFI register.xlsx | Northgate Tower | revisedby Marcus Ellington | 21 Jul, 16:05 |
Basement waterproofing close-out report.pdf | Kestrel House (2013) — Archive | uploadedby Marcus Ellington | 20 Jul, 10:12 |